Office refurbishment in Manchester: should you refurbish your office or move?
For Manchester businesses weighing up an office refurbishment against a move: what each costs on our published rates, the questions that decide it, MEES, and refurbishing while you stay in.
By Dave Groom · Tatton Projects

Refurbishing your Manchester office usually costs less than moving if the building's services and size still work for you. A move adds agents' and legal fees, a new fit-out and reinstating the old floor. A refurbishment avoids those but means working around your staff. On our 2026 rates, a standard Cat B refurbishment is £70 to £110 per sq ft.
The right answer depends on the building more than the budget. This guide sets out the questions that decide it, and what each option involves.
What does an office refurbishment cost in Manchester?
Our published rates for 2026, measured on net internal area and excluding VAT, fees and loose furniture:
- Cat A refresh: £45 to £70 per sq ft
- Standard Cat B: £70 to £110 per sq ft
- High-specification Cat B: £110 to £180 per sq ft and upwards
Refurbishing a floor you're still working in typically adds 10 to 25 per cent, for out-of-hours work, phased handbacks and keeping routes separate. The breakdown of a typical Cat B is in what an office fit-out costs per square foot.
Which questions decide refurbish or move?
Four questions usually settle it:
- Is the floor the right size? If headcount or working patterns have changed a lot, no refurbishment fixes a floor that is too big or too small.
- Can the services take it? Heating, cooling, power and data are the biggest swing in any refurbishment, and old plant may not take more desks.
- What does the lease say? A break date, a renewal or a dilapidations bill changes the sums.
- Can the business work through it? Phasing is possible in most offices, but it takes longer.
Why do the building services matter so much?
On a typical Cat B, mechanical and electrical work is the largest single line, at 30 to 40 per cent of the cost. A floor with recent, well-sized services is a much cheaper refurbishment than one with plant at the end of its life. Why mechanical and electrical is the biggest line goes into why.
A survey of the services before you decide is worth far more than it costs. It is the one thing a floor plan can't tell you.
What does moving cost that refurbishing doesn't?
The move has its own fit-out, at the same rates as above, plus things a refurbishment avoids. Agents' and legal fees on the new lease, furniture and IT moves, and possibly overlapping rent while the new floor is built.
There is the old floor too. Most leases require it to be put back to its original condition, and that dilapidations work is a cost of leaving. Dilapidations and fit-out explains how it's assessed.
Does the building's EPC affect the decision?
It can. Since April 2018, a landlord has not been able to grant a new lease of a commercial property that falls below the minimum energy efficiency standard, currently an EPC of E, unless an exemption applies. If you're renewing in a poorly rated building, upgrade works may be coming anyway.
What EPC E means for letting a building covers what landlords need to do.
Can you refurbish while your staff stay in?
Yes. Most of our commercial work is in occupied buildings. We re-floored the walkways, lobbies and stairs of an occupied office building and built it a new toilet block, showers and bike store, taking floors in sections behind protection and handing them back as they finished.

Before: the existing tiled walkway in the occupied office building, ahead of re-flooring
Our Stockport service centre floor, circa £175,000, was fitted out with ninety-plus staffed positions and the public coming in every day. How to fit out a building without closing it shows how that's phased.
What consents does an office refurbishment need?
Internal work alone is not development under the Town and Country Planning Act, so it needs no planning permission. Building Regulations still apply to fire escape and compartmentation, accessible toilets and new lighting and heating.
If you lease the floor, you'll also need the landlord's licence for alterations. Whoever controls the premises must keep the fire risk assessment up to date as the layout changes.
How do you get a straight answer?
Send us the floor plan, the address and what isn't working. We'll look at the services and give you a written cost plan for refurbishing, which you can set against the cost of a move. More is on our office fit-out in Manchester, commercial refurbishment in Manchester, commercial refurbishment specialists in Manchester and Altrincham and builders in Manchester pages.
Sources
- The Energy Efficiency (Private Rented Property) (England and Wales) Regulations 2015, regulation 27, legislation.gov.uk
- Non-domestic private rented property: minimum energy efficiency standard, landlord guidance, GOV.UK
- Town and Country Planning Act 1990, section 55, legislation.gov.uk
- The Regulatory Reform (Fire Safety) Order 2005, legislation.gov.uk